目标成本 Target costs:是双方协商后预期的成本目标利润 Fix Fee:假定是成本是符合目标的情况下,给卖方的奖励(利润)目标价格 target price :是 目标利润+目标成本.最高限价 Ceiling Price :表示买方最多给的价格分配比率:表示成本节约时奖励或超支时惩罚的分配比率.PTA =Point of Total Assumption 总体假设点,就是买方支出最高限价时,卖方所花费的成本,超过这个点意味着卖方利润会降低aihuau.com计算公式: PTA= [{(Ceiling Price - (Target Cost+Fixed fee))/ buyer‘s Share Ratio } + Target Cost]示例:You are running a project for a customer based on a cost reimbursable contract with the following terms: Target costs: $ 1,000,000; Fix Fee: 100,000; Benefit/cost sharing:80/20; Price ceiling: 1,200,000Which is the PTA (= Point of total assumption, Break point) of the project?A.$1,300,000

B.$1,500,000C.$80,000D.$1,125,000你在为客户做一个项目使用的是成本补偿合同,数据如下:目标成本:1,000,000;固定酬金:100,000;利益成本分担:80/20;最高限价:1200,000下列哪个是项目的PTA(总体假设点,临界点)?A.$1,300,000B.$1,500,000C.$80,000D.$1,125,000答案:D 计算方法:PTA=[{(120 - (100+10))/ buyer‘s Share Ratio } + 100] =10/ buyer‘s Share Ratio +100 =10/0.8+100 =12.5+100=112.5万